Stormwater compliance

Stormwater Compliance Services for California Facilities, Sites, and Cities

SWPPPs, inspections, and SMARTS reporting by certified stormwater staff, kept current with the Industrial and Construction General Permits.

Water surging out of a street drain during a storm event

What we do

Stormwater compliance, start to finish

From the SWPPP to the annual report, we keep the documentation, inspections, and filings your permit requires.

  • SWPPP development and updates

    Stormwater Pollution Prevention Plans prepared by our certified stormwater staff for construction sites under the Construction General Permit and for facilities under the Industrial General Permit, updated when site conditions or the permit change.

  • Inspections and monitoring

    Scheduled site inspections, visual observations, and sampling coordination, with every check documented and kept on record.

  • SMARTS reporting

    Notices of Intent, annual reports, and monitoring data filed in SMARTS, the State Water Board reporting system, on time.

  • MS4 program support

    Annual reports, outfall mapping, standard operating procedures, and program documentation for cities and districts under municipal stormwater permits.

  • Agency coordination

    Responses to State Water Board and Regional Board requests, notices, and inspections, with the documentation to back them up.

  • Compliance calendar

    One calendar for inspections, sampling, training, and filing deadlines, so nothing in the permit is missed.

Which permit covers you

  • Industrial facilities

    Industrial General Permit (Order 2014-0057-DWQ as amended, administratively continued): coverage by SIC code, a SWPPP, sampling, and an annual report certified in SMARTS by July 15. A QISP is required once a facility enters Level 1 status.

  • Construction sites

    Construction General Permit (Order 2022-0057-DWQ), in effect since September 1, 2023: projects disturbing one acre or more, a SWPPP by a QSD, Risk Level 1, 2 or 3 monitoring by a QSP, and an annual report by September 1.

  • Cities and districts

    Municipal (MS4) stormwater permits: program documentation, annual reporting, and outfall records.

July 15Industrial General Permit annual reportFiled in SMARTS each year
Sept 1, 20232022 Construction General Permit in effectOrder 2022-0057-DWQ

Inspections

Commercial and industrial stormwater inspections in California

What the statewide permits require on site, and what we schedule and document for you. A commercial property outside the listed industrial categories may still have local requirements under its city or county municipal permit.

CheckWhenPermit section
Visual observationsAt least once per calendar month, in each drainage area, in daylight and during operating hoursIGP Section XI.A
Sampling event observationsAt the same time samples are collectedIGP Section XI.A
Storm samplingTwo Qualifying Storm Events from July 1 to December 31, and two from January 1 to June 30IGP Section XI.B
Annual Comprehensive Facility Compliance EvaluationOnce each reporting year, covering records, industrial areas, BMPs, and equipmentIGP Section XV
Construction site inspectionsWeekly, before and during qualifying storms, and after storms of 0.5 inches or moreCGP Attachment D, III.C

Construction

Construction stormwater compliance in California

Under the Construction General Permit, compliance starts before the first shovel and runs until the Notice of Termination.

  • Enrollment

    Permit Registration Documents go into SMARTS before construction starts: the Notice of Intent with the Risk Level, site maps, the SWPPP and the annual fee. Coverage begins when SMARTS issues a WDID number.

  • Risk Level

    Sediment risk and receiving water risk combine into Risk Level 1, 2 or 3. Risk Level 2 and 3 sites sample stormwater discharges for pH and turbidity.

  • Inspections

    Weekly, within 72 hours before a qualifying storm forecast, every 24 hours during the event, and within 96 hours after one that measured 0.5 inches or more.

  • QSD and QSP visits

    A QSP inspects monthly. A QSD visits within 30 days of construction starting and twice a year, once from August through October and once from January through March.

Need the plan itself? See our SWPPP services for California sites.

Industrial

Industrial stormwater compliance in California

Under the Industrial General Permit, a facility samples four qualifying storms a year, and results above the numeric action levels start a series of deadlines.

RequirementDeadline
Sampling results submitted in SMARTSWithin 30 days of obtaining all results
Level 1 Evaluation, with QISP assistanceOctober 1 after Level 1 status begins
Level 1 Exceedance Response Action ReportJanuary 1 after Level 1 status begins
Level 2 Action Plan, if exceedances continueJanuary 1 after the reporting year of the exceedance
Annual Comprehensive Facility Compliance EvaluationOnce each reporting year
Annual report certified in SMARTSJuly 15

The process

How it works

  1. Tell us your permit and site
  2. We review your SWPPP and records
  3. We close the gaps
  4. Inspections, sampling, and filings stay on schedule

Construction vs industrial

Construction General Permit vs Industrial General Permit

The two statewide permits most sites fall under, side by side.

RequirementConstruction (Order 2022-0057-DWQ)Industrial (Order 2014-0057-DWQ)
Who is coveredSoil disturbance of one acre or more, or less within a larger common plan of developmentIndustrial activity in a category listed in Attachment A, by SIC code
Who prepares the SWPPPA Qualified SWPPP Developer (QSD)The discharger; a QISP once the facility enters Level 1 status
Field implementationA Qualified SWPPP Practitioner (QSP)The facility, with a QISP for Exceedance Response Actions
Annual report in SMARTSSeptember 1July 15
Ending coverageNotice of TerminationNotice of Termination, or a No Exposure Certification if the facility qualifies

Monitoring, risk levels and every deadline: SWPPP requirements in California.

FAQ

Questions about stormwater compliance

What does stormwater compliance require in California?

Most industrial facilities and construction sites that disturb one acre or more need coverage under a statewide general permit: the Industrial General Permit or the Construction General Permit. Coverage means a current SWPPP, the inspections and monitoring the permit requires, and reports filed in SMARTS. Cities and districts operate under municipal (MS4) permits with their own program and reporting requirements.

Who needs a SWPPP?

Every site covered by the Construction General Permit or the Industrial General Permit needs a Stormwater Pollution Prevention Plan. Under the Construction General Permit, the SWPPP is prepared by a Qualified SWPPP Developer (QSD) and carried out in the field by a Qualified SWPPP Practitioner (QSP). Exodus has certified stormwater staff who prepare SWPPPs and carry out the inspections and monitoring they require.

What is the difference between a QSD, a QSP and a QISP?

On construction sites, the QSD writes and amends the SWPPP and must be retained from the start of the project through Notice of Termination approval, while the QSP carries it out in the field with inspections and sampling. On industrial sites, a QISP is required once a facility enters Level 1 status after sampling exceeds a numeric action level; the QISP prepares the Level 1 Exceedance Response Action report, due in SMARTS by January 1 after Level 1 status begins.

Does a project under one acre need a SWPPP?

Usually not under the Construction General Permit, unless it is part of a larger common plan of development or sale that disturbs one acre or more. Your city or county may still require erosion and sediment controls under its own permit.

Is the Industrial General Permit still in effect?

Yes. Its term ended June 30, 2020, and the State Water Board states it is administratively continued under 40 CFR 122.6 until a new permit is issued, so Order 2014-0057-DWQ as amended remains the permit to follow.

When is the Industrial General Permit annual report due?

The annual report for each reporting year (July 1 to June 30) is certified in SMARTS no later than July 15. Construction General Permit annual reports are due September 1.

What changed with the 2022 Construction General Permit?

Order 2022-0057-DWQ took effect on September 1, 2023, and the 2009 permit was terminated on August 31, 2025. Projects that started under the 2009 permit had to transition to the 2022 requirements, including an updated SWPPP.

Do you inspect commercial and industrial sites?

Yes. We schedule and document the inspections and observations your permit requires, coordinate sampling, and keep the records ready for a Regional Board inspection.

Bring your stormwater program current

Tell us which permit you operate under and send your current SWPPP. We will map the gaps, the deadlines, and what it takes to close them.

Free tool

January 1 is closer than it looks

Validated water loss audits and annual water use reports are due January 1. The free deadline checker shows yours on screen.